4 Townhouses packed with style and quality, with character weatherboard and brick exteriors and chic modern kitchens and bathrooms with stone benchtops.

Project update 7/7/22: 3 down, 1 more slab to go


Project update 6/9/22: Rain Rain go away come again another day! Now the sun is out hopefully we can wrap up this final slab


Project update 27/8/22: last slab, prepped and ready to be poured tomorrow. We cant wait to complete slab stage and smash out this build.


Project update 29/9/22: All slabs are poured and completed!


Project update: 12/10/22: Driveway is Poured!


Project update: 10/11/22: Frames are starting!! Hoping for some nice sunny days so we can smah out these frames and get them up


Project update: 16/11/22: Frames are slowly progressing, needing some sunshine to get these frames finsihed


Project update: 16/02/23: Frames are almost done


Project update: 22/03/23: Frames are up and windows are in


Project update 28/4/23: With frames wrapped up we are full steam ahead on lockup. Brickwork is underway and cladding has been installed to the rear units. It is great to know we will be locked up and dry when winter hits.